Sound Transit Update: Construction Begins Monday

| No Comments

Site preparation for Sound Transit's UW Station construction will start at the E11 parking lot (SW parking lot adjacent to the Husky Stadium) on January 4, 2010 at 7 a.m.

Here is a quick look at the work activities scheduled for January 2010:

• Fencing off a portion of the southwest parking lot of Husky Stadium;
• Ensuring pedestrian and vehicle access around the new 4-acre construction site;
• Clearing trees, removing asphalt and grading the construction site; and
• Utility relocations.

Visit the Tyee website for more information.


You can also visit http://www.soundtransit.org/UWstation for specific project information.